For testing and balancing zone dampers, you must have the CCU connected to its docking station for damper testing to work. Without a connection to the docking station the CCU will have no way to transmit or receive messages from the terminal zones. Damper testing can be achieved by performing the following steps:

 

Step 1. Go to the commissioning screen by selecting the setup icon in the upper right corner of the screen.

CCU-1.PNG

Step 2.  Select the zone damper you want to test from the zones list.

CCU-2.PNG

 

Step 3. Tap on the pairing address of the selected zone to edit the profile settings for that zone.

VAV-C.PNGVVT-C.PNG

 

 

Step 4:  The desired testing Min/Max damper positions for both heating and cooling should be set the same. (See below)

ccu-vvt-c.PNG

 

Note: The same operation should be performed for each zone damper.

 