| Overview

Vacation Schedule for is similar to zone schedule, but unlike a building schedule its just a schedule day or a date range schedule, it tells the system that the zone is on a vacation, and the zone HVAC needs that is required is not the same as in a zone schedule, and the system can operate in a setback or unoccupied mode where usually the desired temperatures are much relaxed than the zone schedule duration or setpoint mode.

Note: Building level vacations do not apply to the zones following zone schedule.

|Accessing Vacation Schedule for Zones

The zone level vacations can be accessed from two places.

Accessing from Zone Screen

From ClimaVision Web UI home page

mceclip0.png

  • Select the site in scope.

The heat map screen is displayed.

mceclip1.png

  • Click Zones.

mceclip0.png

The zone screen is displayed.

  • Select the Zone in scope.

The zone screen displays the zone details.

mceclip2.png

  • Scroll to locate the Vacation schedule section.

mceclip3.png

Accessing from Heatmap Screen

From Heatmap screen.

mceclip4.png

  • Click zone to access the visualization screen.

mceclip5.png

  • Scroll to locate the Zone schedule section under the zone settings.

mceclip6.png

| Setting a Vacation Schedule

To set a new entry for Vacation Schedule

  • Click Add Entry+ next to the vacation.

The Add Vacation Schedule window is displayed.

mceclip4.png

  • Enter a name of the vacation.

mceclip6.png

  • Select a date or a date range you wish to set the vacation for.

mceclip7.png

  • Click Save to confirm and create the vacation schedule for the building.

mceclip7.png

Note: You can also edit an exiting zone vacation to new vacation, by simply clicking, modifying the date or date range.

Once a Zone Vacation is added for the zone screen or visualization screen, the same gets cascaded to the other and in the portals.